Schedule

Currently, 17 projects have been completed, 8 projects are under construction with the anticipated completion date set for fall of 2019, and the remaining 10 projects are anticipated to be complete by the end of 2022.

 

Percent Complete Chart at a Glance:

  • Westbound I-290 Mainline – 69% Complete (Fall 2019)
  • Eastbound I-290 Mainline – 74% Complete (Fall 2019)
  • Eastbound I-290/Ida B. Wells Drive bridge over I-90/94 – 84% Complete (Fall 2019)
  • Ramp NE (Northbound I-290 to Eastbound Ida B. Wells Drive) – 99% Complete (Fall 2019)
  • Van Buren Street Bridge – 94% Complete (Fall 2019)
  • Monroe Street Bridge – 75% Complete (Fall 2019)
  • Water Main and Retaining Wall at UIC along Ramp ES – 86% Complete (Fall 2019)
  • Interchange Ramp Completions – 8% Complete (Fall 2020)
  • Ramp ES (Eastbound I-290 to Northbound I-90/94) – 9% Complete (Fall 2020)